Cowichan Secondary School Replacement Project

The Cowichan Secondary School Replacement Project was announced December 2019, and much work has occurred since that time. The new school will be built for 1,100 students.

Cowichan Secondary School Replacement Project

Client: The Board Education of School District No. 79 (Cowichan Valley)
Project Cost: The total anticipated construction budget is approximately $62.0 million and the total project budget allocation is $82.1 million.
Partner: TBD
Project Status: In procurement
Project Report:
Project Website:
Project Image:

Milestones

Request for Qualifications issued July 7, 2020
Request for Qualifications closed Sept. 10, 2020
Request for Proposals issued January 14, 2021
Contract award
Construction to begin
Construction completed Spring 2024

Project Updates

Procurement Documents

Project Map

Project Contacts