John Hart Generating Station Replacement Project

The John Hart Generating Station Replacement Project involves the replacement of the existing six-unit, 126 MW generating station.

John Hart Generating Station Replacement Project

Project Details

Project Description: The proposed John Hart Generating Station Replacement Project, located in Campbell River, involves the replacement of the existing six-unit, 126 MW generating station. Project benefits will include improved seismic safety, protecting fisheries resources, along with increased power capacity and reliability.

Client: BC Hydro
Capital Cost:
Partner:
Project Status: Under construction
Project Report:
Project Website: Click to access website
Case Study:
High Res Photo: Click to access photo

Milestones

Request for Qualifications issued March 13, 2012
Request for Qualifications closed April 25, 2012
Shortlist announced July 6, 2012
Request for Proposals issued June 27, 2012
Contract award February 28, 2014
Construction to begin
Construction completed

Project Updates

Procurement Documents

Project Contacts

Project Contact:

Dawn Hart
Email: Dawn.hart@bchydro.com

Media Contact:

Stephen Watson
BC Hydro
Phone: (250) 755-4795