South Fraser Perimeter Road Project

The South Fraser Perimeter Road (SFPR) project is part of the Province's Gateway Program, which will improve roads and bridges for people, goods and transit in Metro Vancouver. The SFPR, approximately 40 km long, is a new four-lane, 80 km/hr route along the south side of the Fraser River, extending from Deltaport Way in Southwest Delta to 176th Street.

Sign up here to receive emails about future projects, news on current project developments and information about Partnerships BC programs

South Fraser Perimeter Road Project

 

 

PROJECT DETAILS:

 

Project Description:
The South Fraser Perimeter Road (SFPR) project is part of the Province's Gateway Program, which will improve roads and bridges for people, goods and transit in Metro Vancouver. The SFPR, approximately 40 km long, is a new four-lane, 80 km/hr route along the south side of the Fraser River, extending from Deltaport Way in Southwest Delta to 176th Street, including connections to Highway 1, 15, 17, 91, 99 and to TransLink's Golden Ears Bridge Connector Road.

The SFPR will offer goods movers an efficient transportation corridor, while restoring municipal roads as community connectors by reducing truck and other traffic in residential neighbourhoods. Project construction is scheduled for completion in 2013. The SFPR will be jointly funded by the federal and provincial governments.

Client: Ministry of Transportation and Infrastructure
Capital Cost: $658 million
Partner: Fraser Transportation Group
Project Status: Under construction
Project Report: Click to access report
Project Website: Click to access website
Case Study: Click to access case study
High Res Photo: Click to access photo
South Fraser Perimeter Road Project

 

 

PROJECT AWARDS:

 

2010

  • CCPPP National Awards for Innovation and Excellence – Award of Merit, Financing category

 

MILESTONES:

 

 

Request for Qualifications issued July 29, 2008
Request for Qualifications closed September 29, 2008
Shortlist announced January 12, 2009
Request for Proposals issued April 9, 2009
Contract award July 14, 2010
Construction to begin 2010
Construction completed 2013/14

 

PROJECT UPDATES:
CLICK TO VIEW AND/OR CLOSE PROJECT UPDATES

 

 

PROCUREMENT DOCUMENTS:
CLICK TO VIEW AND/OR CLOSE PROCUREMENT DOCUMENTS

 

 

 

PROJECT CONTACTS:

 

 

Project

Contact:

Geoff Freer

Gateway Program

Tel: (604) 940-7987

Media Contact:

Liz Bicknell
Communications Director
Ministry of Transportation and Infrastructure
Public Affairs Bureau
Tel: (250) 387-7787